Menawethan timeline

CGI-Menawethan-July-2025-1200x800.jpg

31st October 2025 – Launch

Menawethan will exit the dock for the first time, marking the start of the final phase of her build.

1st November 2025 – Commissioning begins

Testing and running of the vessel’s systems and equipment will get underway.

January 2026 – Sea trials

A week-long programme of sea trials will take place down the delta to test performance and handling with Steamship crew representatives.

March 2026 – Delivery voyage

Menawethan will begin her journey from Vietnam to Europe.

April 2026 – Arrival in France

The vessel will arrive in France for final preparations ahead of delivery.

May 2026 – Arrival in the UK

Menawethan is due to arrive in the UK ahead of crew familiarisation, training, and final checks before entering service.