New vessels – April 2025 updates
Scillonian IV
Progress on Scillonian IV in April has been making great strides. Units 8.2, 10, and 18 have been successfully erected dockside, while the engine room has been rotated and lowered into the dock for integration. Fabrication work has commenced in the workshop on units 19 and 11. Additionally, outfitting activities are now underway in both the technical and the engine room.
Menawethan
Progress on Menawethan in April has included the installation of the port outer stern tube and sea grids. Preparation work continues in the Captain’s cabin for fitting bulkhead panels. The hull draft marks were accurately confirmed using a laser theodolite and have now been welded in place. Additionally, painting is currently underway in the steering gear compartment.