Scillonian IV timeline

CGI-Scillonian-IV-July-2025-1200x800.jpg

March 2026 – Launch

Scillonian IV will be launched from the dock, beginning the next stage of her build.

June 2026 – Sea trials

A week-long programme of sea trials will take place down the delta to test vessel performance and handling.

July 2026 – Delivery voyage

Scillonian IV will sail under her own power and will begin her journey from Vietnam to Europe. While the original plan was to transit via the Suez Canal, advice from officials due to ongoing instability in the Middle East means the vessel will now travel around the Cape of Good Hope, adding approximately 40 days to her delivery journey.

September 2026 – Arrival in France

Scillonian IV will arrive in France for final preparations ahead of UK delivery.

October 2026 – Arrival in the UK

The vessel will reach the UK to begin berthing trials and crew familiarisation training.

March 2027 – Entry into service

Following successful trials and training, Scillonian IV will enter passenger service, delivering faster, more comfortable, and sustainable travel to the Isles of Scilly.